Thursday 2 November 2023

Province tries to get building of new Fredericton justice building going again

 

Province tries to get building of new Fredericton justice building going again

After attracting a single, too-high bid in earlier effort, province moves to hire construction management firm

The New Brunswick government is renewing efforts to build a new justice building in downtown Fredericton.

The province is now seeking a construction management firm to continue the courthouse work, which got as far as the frame before it was stopped in August.

An earlier tender was cancelled because the sole bid came in at an amount substantially higher than what the government wanted to spend.

"It should be more of an economical approach to the whole project," Transportation and Infrastructure Minister Richard Ames told reporters at the legislature Wednesday.

The only response to the province's request for proposals "came in way out of whack," Ames said.

"Like it was just cahootles of money over [budget], so what we did is we sent out another RFP that closes in November and the project manager will take care of that."

A smiling man standing outdoors in a grey suit and purple dress shirt Transportation and Infrastructure Minister Richard Ames says the use of a construction management firm should be a more 'economical' approach to getting the justice building finished. (Jacques Poitras/CBC)

The government under Premier Blaine Higgs announced it would build a new courthouse on King Street after deciding to axe an earlier plan for one that would be attached to the Centennial Building, just down the street.

Earlier tenders had been issued to prepare the site, starting in December 2021, as well as to erect the steel frame of the building, which was completed this past spring.

The bulk of the remaining work was to be done by a contractor starting this year, and on July 7, the province issued a tender for that work.

By the time the tender closed on July 13, the only company to respond was EllisDon, which submitted a bid $30 million higher than the province's original budget of $60 million for the project.

The Centennial Building in downtown Fredericton.   An earlier plan called for a new courthouse attached to the Centennial Building on King Street. (John Leroux/ Supplied)

In an email to CBC News, Department of Transportation and Infrastructure spokesperson Tyler McLean said the construction management model is working well in other jurisdictions, as it removes some of the risk that would typically be the responsibility of a general contractor.

"Construction management is advantageous in periods of unstable markets and price uncertainty," McLean said.

"It transfers the risk of future price increases from the contractor to the owner. In a traditional tender, this risk is carried by the contractor."

The latest tender for the justice building was issued last Thursday, and will remain open until next Thursday. 

McLean said a construction management firm is expected to be in place in December, and construction activity is expected to resume next year.

McLean declined to say whether the budget for the project has changed, saying it won't be revealed in advance of the closing of the request for proposals.

Shifting the risk

When a general contractor is hired, they take on the bulk of the risk by having to ensure the project gets completed on time at a price decided upfront, said Lloyd Waugh, a professor of civil engineering at the University of New Brunswick.

With a construction management firm, phases of the project will likely be tendered out separately as it progresses, which leaves the province vulnerable to future price increases in labour and materials.

Lloyd Waugh in a portrait photo. The use of a construction management company transfers the risk to the provincial government, as opposed to a general contractor, said Lloyd Waugh, honorary research professor at the University of New Brunswick's civil engineering department. (Submitted by Lloyd Waugh)

Amid the market volatility seen recently, costs could continue to rise, which is a possibility that general contractors typically factor into their bids.

Alternatively, prices for materials and labour could also get cheaper in the future, which would be good for the province, Waugh said.

"If you think of interest rates, and you know, potential for construction costs to go down over the next year, then this leaves them [provincial government] the opportunity to benefit from those costs going down," Waugh said.

"But it also leaves from the potential that costs go up more than people are currently expecting, then they'll get stuck with the higher cost."

Lone bid should be concerning, prof says

With a construction management firm, the provincial government will be able to have more oversight on how much money is spent on the project, said Lavagnon Ika, professor of project management at the University of Ottawa.

However, he said the lone $93-million bid for the first tender should be raising warning flags for the provincial government.

 Lavagnon Ika sits in a room wearing a jacket.The fact that the province received a lone bid earlier of $93 million raises questions about whether it can get the justice building finished within its $60 million budget. (Zoom/CBC)

While a construction management firm might be able to get the work done within the $60-million budget, there's no guarantee that's possible given how much the costs of materials and labour have gone up.

"Why is it that we have only one bidder?" said Ika, referring to the earlier tender.

"That's the challenge. That's the question that we need to look into."

ABOUT THE AUTHOR


Aidan Cox

Journalist

Aidan Cox is a journalist for the CBC based in Fredericton. He can be reached at aidan.cox@cbc.ca and followed on Twitter @Aidan4jrn.

CBC's Journalistic Standards and Practices
 
 

88 Comments

 

David R. Amos
I suspect if Higgy had left things alone there would be a new courthouse attached to the Centennial Building by now
 
 
 
 
Kyle Woodman 
Another failure by the Higgs government. 
 
 
David R. Amos  
Reply to Kyle Woodman 
Welcome back to the circus 
 
 
Kyle Woodman
Reply to David R. Amos   
Hahaha. Indeed David, indeed.  
 
 
 
 
Marcel Belanger
The great canceler cost the province $30 + millions when he shut down the original project, which it should be noted would have been finished 3-4 years ago. Also added to those costs is the rent being paid for offices that are required and for all those temporary court rooms, we’ll probably never know how much those have cost but it probably would have paid for the new courthouse a few times over. This is the premier being called a financial genius by some, not many mind you, but some, and those are getting fewer and fewer all the time. Bring on those Canada games, another fiscal genius project that we’ll never what it will cost. 
 
 
Ronald Miller 

Reply to Marcel Belanger
 
 
Kyle Woodman 
Reply to Ronald Miller
Surely you jest.   
 
 
David R. Amos  
Reply to Kyle Woodman
Par for the course 
 

No comments:

Post a Comment